+38 048 730 57 40

+38 048 730 57 31

 
 
 

S-Engineering has completed a major project to build a new cooling tower for cooling vacuum pumps of the pellet production department at the Poltava Mining and Processing Combinat. The facility was commissioned in late June.

The turn-key project included the design of automated process control and electrification systems of the facility, as well as the development of software, manufacturing of shield equipment, installation and commissioning at the facility, complex testing.

The automated process control system ensures regulation and maintenance of the required parameters in the cooling tower operation on the line for removing moisture from the pulp, and also minimizes the use of human resources at this production site. The project uses cabinet equipment based on Siemens converters, which was manufactured on its own production complex S-Engineering. All the equipment has passed the tests that confirmed compliance with the requirements.