What was done
For the Yantar brewery in Nikolaev, the following projects have been implemented:
- A set of works to modernize the automation system and power supply for CIP 3.4 bottle washing lines.
- Complex of works on modernization of the conveyor control system of the bottling line No. 3: supply of equipment, installation and commissioning.
- Complex of works on modernization of the system of thermometry of grain storage silos.
- Modernization of the automated control system for a continuous beer pasteurizer manufactured by KHS.
- Design and construction of transformer substation No. 5.
- Design, manufacture, installation and commissioning of fire alarm systems.
- Design, installation and adjustment of the dispatching and technical accounting system for the 6 kV switchgear of the RP-71 substation of the Yantar brewery.
- Design, installation and commissioning of an automated process control system for a warehouse for storing detergents and a power supply system for a tank warehouse for caustic soda.
The following projects were completed for the Desna brewery in Chernihiv:
- Audit of power communications of the Chernihiv branch of OAO Sun InBev Ukraine.
- A set of works on the development and implementation of an automated control system for a module for monitoring and visualizing beer quality parameters during bottling: design, software development, manufacture and supply of equipment and materials, installation and connection of instrumentation, electrical installation and commissioning.
- A set of works on the implementation of a system for collecting and storing beer quality control data: design, software development, manufacture and supply of equipment and materials, installation and connection of instrumentation, electrical installation and commissioning.
- Reconstruction of the main switchboard MSB-0.4kV of the transformer substation No. 2 of the water treatment and air preparation shop. Design, manufacture, installation and commissioning.
- Reconstruction of the main switchboard MSB-0.4 kV of the transformer substation No. 4 of the beer bottling and bottle washing line. Design, manufacture, installation and commissioning.
- Construction and equipping of transformer substation No. 6 for power supply of a new bottling line.
For the Rogan brewery in Kharkov, the following was done:
- Design, manufacture, installation and adjustment of the power supply system for the canned beer bottling line.