What was done
- For Turkmencement, S-Engineering specialists implemented a comprehensive selection and supply of spare parts manufactured by Siemens, as well as the modernization of the hardware of the server equipment of the process control system based on PCS v5.2 software.
- For the LAFARGE cement plant, a cement mill was modernized and a control panel was developed.
- For the Bakhchisaray Cement Plant, a set of works was completed to develop design documentation, software, perform installation and commissioning, manufacture and supply of equipment for automation systems based on Siemens PCS7 technology and power supply for the coal preparation complex of kilns No. 1 and No. 2. And also a set of works was carried out for the automated control system of the slag drying department of this plant.
- For Dyckerhoff Zement International, the design and supply of equipment for the access control and management system was carried out. Installation and adjustment of the access control and management system and the security television system.