What was done
- In 2021, S-Engineering carried out the next stage of modernization of the Vesnyanka elevator in the village of Starokonstantinov (one-time storage capacity of the elevator is 125 thousand tons.) A modernization project was developed, equipment was supplied, electrical installation was completed, the existing PLC and SCADA software was finalized and commissioning works were carried out in the following sections:
– power supply of grain dryers (cable routes and power switch cabinet);
-automation (adding new pieces of equipment to existing schemes and software);
– obstruction lights (two lights for the new elevator tower);
– lightning protection (for a new elevator tower;
– adding new equipment to the software and automatic operation of the Vesnyanka elevator;
-implemented update of routes at the enterprise.
- In 2013-2014 for the Vesnyanka elevator in Starokonstantinov, Khmelnitsky region. a set of works was carried out to create a power supply system and an automated process control system for a site for receiving, storing and primary processing of grain with a capacity of 100 thousand tons: design work, software development, production and supply of equipment, installation and commissioning. Also, a set of works was completed to create a power supply system and automated process control systems, taking into account the construction of the 2nd elevator tower for the area of acceptance, storage and primary processing of grain with a capacity of 140 thousand tons, design work, software development, production and supply of equipment, installation and commissioning.
- For the elevator in c. Budishche, Cherkasy region a comprehensive project was completed to introduce a power supply system and an automated process control system for a site for receiving, storing and primary processing of grain with a capacity of 60 thousand tons: design work, software development, production and supply of equipment, installation and commissioning. The storage capacity of the elevator is 60 thousand tons.
- For the elevator in the village. Smolino, Kirovograd region a set of works was implemented to modernize the power supply system and automated control system as part of the reconstruction of the working tower of the elevator: design, software development, supply of equipment and materials, installation and commissioning. The storage capacity of the elevator is 60 thousand tons.
- For the elevator in c. Devladovo, Dnepropetrovsk region (storage – 60 thousand tons) a set of works was completed on the development and implementation of remote access systems in the automated control systems of the elevator. Design, software development, installation and commissioning of the power supply system and automated process control systems for areas for receiving, storing and primary processing of grain in the elevator. The storage capacity of the elevator is 60 thousand tons.