What was done
A project was implemented for power supply, integrated automation of technological processes of coal grinding and its dosing into the burners of the main furnaces of the plant:
- A set of works on the creation of a power supply system and an automated process control system for a line for palletizing cement bags.
- Comprehensive audit of process control systems.
- Supply and installation of instrumentation equipment and aspiration section, commissioning.
- Design, supply of equipment, installation and commissioning of equipment for the project “Gas analysis of the coal silo storage area”.
- Electrification and integrated automation of technological processes of coal grinding and dosing of coal dust.
The implementation of these projects allowed the plant to completely abandon the use of natural gas and increase the efficiency of clinker burning.