What was done
For the company “Ukratlantik” several projects were implemented:
- Complex projects for the development and implementation of an internal and external electric lighting system for a new convector production workshop.
- Complex supply of materials and installation works for connecting the technological equipment of the convector production workshop.
- A set of works for the design, supply of equipment, installation, commissioning and commissioning of the 10 and 0.4 kV power supply system of a new production building for climate control equipment.